There are \(n\) employees at Bersoft company, numbered from \(1\) to \(n\). Each employee works on some days of the week and rests on the other days. You are given the lists of working days of the week for each employee.
There are regular days and holidays. On regular days, only those employees work that have the current day of the week on their list. On holidays, no one works. You are provided with a list of days that are holidays. The days are numbered from \(1\) onwards, day \(1\) is Monday.
The company receives \(k\) project offers they have to complete. The projects are numbered from \(1\) to \(k\) in the order of decreasing priority.
Each project consists of multiple parts, where the \(i\)-th part must be completed by the \(a_i\)-th employee. The parts must be completed in order (i. e. the \((i+1)\)-st part can only be started when the \(i\)-th part is completed). Each part takes the corresponding employee a day to complete.
The projects can be worked on simultaneously. However, one employee can complete a part of only one project during a single day. If they have a choice of what project to complete a part on, they always go for the project with the highest priority (the lowest index).
For each project, output the day that project will be completed on.
Output
Print \(k\) integers — the \(j\)-th value should be equal to the day the \(j\)-th project is completed on.